¿Qué significa 24594 ?
The PATT instruction cannot take ownership of the equipment phase because it is currently in an unscheduled or inhibited state, or the task containing the equipment phase is inhibited.
Causas comunes
- The operational state of the equipment phase or its controlling task is preventing ownership acquisition.
Pasos de reparación & Lista de verificación
Haga clic en los pasos para seguir su progreso.
- 1
Verify the scheduling and inhibition status of the equipment phase — ensure it is scheduled and not in an inhibited state.
- 2
Check the status of the controller task containing the equipment phase — confirm the task itself is enabled and not inhibited.