What does 7584 mean?
The supply unit (LSU) did not become ready (e.g., main contactor/breaker closing) within the expected timeframe. This indicates a problem with the LSU's pre-charging or readiness sequence. The drive cannot operate without a ready supply unit.
Additional Steps
Steps 1–2 are listed in Priority Fix.
- 3
Ensure the supply unit is enabled, allowed to start, and can be controlled by the inverter unit (e.g., not in local control mode).