The inverter type (e.g., sr0025_3) has been changed, typically at the factory or during drive implementation, and a power cycle is required to validate this change. This alarm prompts the user to switch off the control board power to finalize the hardware reconfiguration and allow the drive to operate with the new settings.
Click steps to track your progress.
Locate the main incoming power disconnect for the drive (e.g., circuit breaker L1, L2, L3) and switch it to the OFF position.
Confirm that all drive status LEDs are extinguished and the control panel display is off, indicating complete discharge of DC link capacitors; wait at least 5 minutes to ensure full discharge.
Switch the main incoming power disconnect (e.g., circuit breaker L1, L2, L3) back to the ON position to re-energize the drive.
Monitor the drive's startup sequence and check if the 'FF39' alarm clears and normal operation can be initiated.
If the alarm persists, power off again and verify the physical seating and connection of any recently replaced internal hardware components (e.g., control board, power module).
Access the drive's parameter settings (e.g., P0-03 Drive ID) after the power cycle to ensure the correct inverter type is now recognized and displayed.