Schneider Electric · XW Pro NA Operation Guide
This fault indicates an over-voltage condition between L1 and L2 phases detected by the anti-islanding protection, exceeding the AC qualification limits. This mechanism ensures the inverter disconnects from the grid if grid power is unstable or absent, preventing dangerous backfeeding and potential damage to equipment.
Click steps to track your progress.
Using a true RMS multimeter, measure and record the L1-L2 phase-to-phase voltage at the inverter's input terminals over an extended period (e.g., 30 minutes).
Compare the measured L1-L2 voltage values to the inverter's configured AC qualification limit parameter (e.g., P_Grid_Volt_Max_L1L2_Qual).
Inspect the integrity of the AC input connections for phases L1 and L2 at the inverter (e.g., Terminals L1, L2) for loose terminals or poor contact.
Consult the utility provider to inquire about recent grid stability, voltage anomalies, or work performed on the local distribution network.
If grid voltage is stable and within acceptable range, perform an internal inverter diagnostic on the voltage sensing hardware or replace the control board.